![]() |
CIVIL ENGINEER STANDARD DATA |
*WEIGHT OF MATERIALS:-
👆
Click Here
50 mm J bolt : 751 No’s / 52 Kg
40 mm J bolt : 883 No’s / 54 Kg
2” nails : 385 No’s / Kg
3” nails : 118 No’s / Kg
4" nails : 72 No’s / Kg
Binding wire : 170 rings /Kg
*SIMPLEX FORMULA:-
U = (N /L) x {(W x H) / (1 + S)} x Sq.rt {(L/50)}
U = Ultimate load in tones
N = Number of blows
L = Pile length in feets
W = Weight of hammer in tones
H = Height of fall in feet.
S = Set for 1 blows in Inch
Safe load = (ultimate load/ 2.5)
Factor of safety = 2.5
10 blows = below 10 MM
*Thread couplers:- (For Column lapping)
Couplers for reinforcing bars 20 mm to 28 mm crimped sleeve.
*Slump As Per IS 456:-
Lightly reinforced 25 – 75 mm
Heavily reinforced 75 – 100 mm
Trench fill (insitu & Tremie) 100 – 150 mm
(For Termie vibrator not required)
*Durability:-
- The Environment.
- Cover to Steel.
- Type and quality of the constituent material.
- Cement content and Water Cement ratio.
- Workmanship to obtain full compaction.
- Compaction and efficient curing.
*Accuracy of measuring equipment in batching plant:-
- Cement : + 2%
- Aggregate : + 3%
- Admixture : + 3%
- Water : + 3%
- Mixing time : 2 minutes for one mixing.(site Mixing)
*TOLERANCE:-
1)Form work:-
In C/S for columns & Beams deviation is = + 12mm more (or) - 6mm less in size
In footing plan = + 50 mm more (or) – 12 mm less size
In depth = + 0.05 D (specified thickness).
2)Reinforcement:-
- For effective depth D < 200mm =10mm.
- For effective depth D >200mm=+15mm.
- For Cover to reinforcement = + 10mm
- Maximum freefall of concrete = 1.50 m height.
*TOLERANCE ON DIA IN LENGTH:-
- 0-25mm = + 0.5 %
- 25-35mm = + 0.6 %
- 35-50mm = + 0.8 %
*TOLERANCE ON WEIGHT PER METRE:-
- 0-10mm = +7%
- 10-16mm = + 5%
- 16 and above = + 3%
*TOLERANCE FOR CUTTING
*TEST FOR SILT & CLAY:-
- Take 200 ml measuring cylinder fill sand up to 100ml mark.
- Add 150ml of water and shake well.
- Allow it to settle for 3 hrs.
- Measure the total height and height of clay.
- Calculate the clay and silt in total sand.
- Clay and Silt should not exceed 3% by weight (or) 8-10% by volume.
- For crushed sand Clay and Silt should not exceed 15% by weight.
*ORGANIC IMPURITIES:-
- Don’t dried the specimen before testing.
- Take 250 ml measuring cylinder.
- Add 75 ml of water with 3% of Sodium Hydroxide. Fill sand layer to 125 ml
- Make the volume up to 200ml by adding more of sodium hydroxide solution.
- Shake well allow it to stand for 24 hrs.
- If the solution becomes darker than straw yellow colour then the sand has to be
- Tested for further by casing mortar cubes for 7 & 28 days is not less than 95%.
8. If the solution is lighter or just straw yellow colour the sand can be used for
concreting without any further test.
*QUANTITIES REQUIRED:-
Plastering (CM 1:3) = 1.50 bags / 10 m2.
Plastering (CM 1:5) = 1.05 bags / 10 m2.
Ceiling Plastering (CM 1:3) = 48 kg / 10 m2.
Brick work (CM 1:5) = 86 Kg / 10 m3.
Brick work (CM 1:6) 9” thick = 80.64 Kg / 10 m3.
Brick work (CM 1:3) 4½” thick = 15.46 Kg / 10 m3.
Lime for white washing = 10 Kg/100 m2.
Painting = 10 ltr/ 100 m2.
Distemper 1st coat = 6.5 Kg / 100 m2
Distemper 2nd coat = 5.0 kg / 100 m2.
Snowcem 1st coat = 30 Kg / 100 m2
Snowcem 2nd coat = 20 Kg / 100 m2
Paint ready mixed one coat = 10 ltr / 100 m2.
Weathering Course = 7.68 Kg / m2.
Flooring = 8.10 kg / m2.
Pressed tiles for weathering course (CM 1:3)= 7.68 Kg / 10 m2.
Granolithic floor finish = 8.10 Kg / 10 m2.
Plastering (CM 1:5) = 1.05 bags / 10 m2.
Ceiling Plastering (CM 1:3) = 48 kg / 10 m2.
Brick work (CM 1:5) = 86 Kg / 10 m3.
Brick work (CM 1:6) 9” thick = 80.64 Kg / 10 m3.
Brick work (CM 1:3) 4½” thick = 15.46 Kg / 10 m3.
Lime for white washing = 10 Kg/100 m2.
Painting = 10 ltr/ 100 m2.
Distemper 1st coat = 6.5 Kg / 100 m2
Distemper 2nd coat = 5.0 kg / 100 m2.
Snowcem 1st coat = 30 Kg / 100 m2
Snowcem 2nd coat = 20 Kg / 100 m2
Paint ready mixed one coat = 10 ltr / 100 m2.
Weathering Course = 7.68 Kg / m2.
Flooring = 8.10 kg / m2.
Pressed tiles for weathering course (CM 1:3)= 7.68 Kg / 10 m2.
Granolithic floor finish = 8.10 Kg / 10 m2.
*TRAPEZOIDAL FOOTING FORMULA:-
Volume,
V = (L x B x D) = H/3{A1 + A2 + sq.rt(A1+A2)}
Where A1 = L x B
A2 = l x b B
H = D-d (Overall depth of footing – depth of
Rectangular footing.
![]() |
TRAPEZOIDAL FOOTING |
*CMENT REQUIREMENTS:-
M10 : 210 Kg
M20 : 320 Kg
M25 : 340 Kg
M30 : 380 Kg
M35 : 410 Kg
M40 : 430 Kg
M45 : 450 Kg
M50 : 450 + M.S 7.5%
*Thumb rule requirement of standard materials and standard
calculation in high raised building:-
- Steel =3 to 5 kg / sft
- Cement =.5bags/ sft
- RMC =.05 m3/sft
- Block =12.5 nos /sqm
- Electrical cost = Rs 133/sft
- Plumbing cost = Rs 126/sft
- Fire fighting cost = Rs 40/sft
- External development = Rs 94.5/sft
- Civil works-Structure = RS 751.25/sft
- 200 mm in cm 1:6 =0.124Bags /sqm
- 200 mm in cm 1:4= 0.206 bags/sqm
- 150 mm in cm 1:6= 0.093 bags/sqm
- 150mm in cm 1:4= 0.144 bags/sqm
- 100 mm in cm 1:4= 0.103 bags/sqm
- Ceiling plastering= 0.11 bags/sqm
- Wall plastering =0.09 bags/sqm
- Rough plastering =0.09 bags/sqm
- Duct plastering= 0.09 bags/sqm
- External plastering= 0.175 bags/sqm
- lathen plastering =0.55 bags/sqm
- stucco plaster =0.175 bags/sqm
- 100 mm plaster band= 0.012 bags/rmt
- pcc 1: 4: 8= 3.4 bags/cum
- pcc 1:5:10= 2.52 bags/cum
- pcc 1:3:6= 4.2 bags/cum
- pcc 1:2:4 =6.02 bags/cum
- 230 mm brick =0.876 bags/cum
- 115 mm brick work= 0.218 bags/cum
- vdf 100 mm thick =0.82 bags/sqm
- granolithic flo oring 40 mm= 0.35 bags/sqm
- granolithic flooring 20 mm= 0.28 bags/sqm
- anti-skid= 0.28 bags/sqm.
- ceramic= 0.28 bags/sqm.
- vertified tile flooring =0.28 bags/sqm.
- vertified tile dado 0.27 bags/sqm.
- ceramic dado =0.27 bags/sqm.
- marble flooring =0.3 bags/sqm.
- 100 mm heigh marble skerting =0.027 bags/rmt.
- marble glading =0.27 bags/sqm.
- terracota tle flooring =0.3 bags/sqm.
- mangalore tile= 0.3 bags/sqm.
- Door frame fixing= 0.17 bags/sqm.
- water proofing for sunken slab= 0.23 bags/sqm.
- water proofing for walls= 0.23 bags/sqm
- water proofing for balcony/toilets =0.65 bags/sqm.
*Labour Productivity:-
Brick work :-
1 mason:-
1 Men mazdoor. 1.25 cm
1 Women Mazdoor.
Wall Plastering :-
1 mason
1 Men mazdoor 10 sqm
1 Women Mazdoor
Ceiling Plastering :-
1 mason
1 Men mazdoor 8 sqm
1 Women Mazdoor
External Plastering:-
1 mason
1 Men mazdoor. 8 sqm
1 Women Mazdoor.
Blockk work 8”:-
1 mason
1 Men mazdoor 10 sqm
1 Women Mazdoor.
Blockk work 6” :-
1 mason
1 Men mazdoor. 8 sqm
1 Women Mazdoor.
Blockk work 4” :-
1 mason
1 Men mazdoor 8 sqm.
1 Women Mazdoor
Carpenter :-
1 Skilled
1 Un skilled:- 4 Sqm
Bar bender :-
1 Skilled
1 UN skilled 200Kg
Tile work:-
1 Mason
1M Mazdoor. 10 Sqm
Painter :-
skilled OBD 600 Sft
Emulsion. 800 Sft.
Putty 600 Sft
Primer. 800 Sft
0 Comments