CIVIL ENGINEER STANDARD DATA



*WEIGHT OF MATERIALS:-

         ðŸ‘†
    Click Here


50 mm J bolt : 751 No’s / 52 Kg

40 mm J bolt : 883 No’s / 54 Kg

2” nails : 385 No’s / Kg

3” nails : 118 No’s / Kg

4" nails : 72 No’s / Kg

Binding wire : 170 rings /Kg



*SIMPLEX FORMULA:-


U = (N /L) x {(W x H) / (1 + S)} x Sq.rt {(L/50)}


U = Ultimate load in tones

N = Number of blows

L = Pile length in feets

W = Weight of hammer in tones

H = Height of fall in feet.

S = Set for 1 blows in Inch


Safe load = (ultimate load/ 2.5)

Factor of safety = 2.5

10 blows = below 10 MM


*Thread couplers:- (For Column lapping) 


Couplers for reinforcing bars 20 mm to 28 mm crimped sleeve.


*Slump As Per IS 456:- 


Lightly reinforced 25 – 75 mm

Heavily reinforced 75 – 100 mm

Trench fill (insitu & Tremie) 100 – 150 mm
(For Termie vibrator not required)


*Durability:-


  • The Environment.
  • Cover to Steel.
  • Type and quality of the constituent material.
  • Cement content and Water Cement ratio.
  • Workmanship to obtain full compaction.
  •  Compaction and efficient curing.


*Accuracy of measuring equipment in batching plant:-


  • Cement : + 2%
  • Aggregate : + 3%
  • Admixture : + 3%
  • Water : + 3%
  • Mixing time : 2 minutes for one mixing.(site Mixing)



*TOLERANCE:-

1)Form work:-


In C/S for columns & Beams deviation is = + 12mm more (or) - 6mm less in size
In footing plan = + 50 mm more (or) – 12 mm less size
In depth = + 0.05 D (specified thickness).



2)Reinforcement:-


  1. For effective depth D < 200mm =10mm.
  2. For effective depth D >200mm=+15mm.
  3. For Cover to reinforcement = + 10mm
  4. Maximum freefall of concrete = 1.50 m height.


*TOLERANCE ON DIA IN LENGTH:-

  1. 0-25mm = + 0.5 %
  2. 25-35mm = + 0.6 %
  3. 35-50mm = + 0.8 %

*TOLERANCE ON WEIGHT PER METRE:-


  1. 0-10mm = +7%
  2. 10-16mm = + 5%
  3. 16 and above = + 3%

*TOLERANCE FOR CUTTING

*TEST FOR SILT & CLAY:-


  1. Take 200 ml measuring cylinder fill sand up to 100ml mark.
  2. Add 150ml of water and shake well.
  3. Allow it to settle for 3 hrs.
  4. Measure the total height and height of clay.
  5. Calculate the clay and silt in total sand.
  6. Clay and Silt should not exceed 3% by weight (or) 8-10% by volume.
  7. For crushed sand Clay and Silt should not exceed 15% by weight.


*ORGANIC IMPURITIES:-


  1. Don’t dried the specimen before testing.
  2.  Take 250 ml measuring cylinder.
  3. Add 75 ml of water with 3% of Sodium Hydroxide. Fill sand layer to 125 ml
  4. Make the volume up to 200ml by adding more of sodium hydroxide solution.
  5. Shake well allow it to stand for 24 hrs.
  6. If the solution becomes darker than straw yellow colour then the sand has to be
  7. Tested for further by casing mortar cubes for 7 & 28 days is not less than 95%.
8. If the solution is lighter or just straw yellow colour the sand can be used for
concreting without any further test.

*QUANTITIES REQUIRED:-


Plastering (CM 1:3) = 1.50 bags / 10 m2.

Plastering (CM 1:5) = 1.05 bags / 10 m2.

Ceiling Plastering (CM 1:3) = 48 kg / 10 m2.

Brick work (CM 1:5) = 86 Kg / 10 m3.

Brick work (CM 1:6) 9” thick = 80.64 Kg / 10 m3.

Brick work (CM 1:3) 4½” thick = 15.46 Kg / 10 m3.

Lime for white washing = 10 Kg/100 m2.

Painting = 10 ltr/ 100 m2.

Distemper 1st coat = 6.5 Kg / 100 m2

Distemper 2nd coat = 5.0 kg / 100 m2.

Snowcem 1st coat = 30 Kg / 100 m2

Snowcem 2nd coat = 20 Kg / 100 m2

Paint ready mixed one coat = 10 ltr / 100 m2.
Weathering Course = 7.68 Kg / m2.

Flooring = 8.10 kg / m2.

Pressed tiles for weathering course (CM 1:3)= 7.68 Kg / 10 m2.

Granolithic floor finish = 8.10 Kg / 10 m2.


*TRAPEZOIDAL FOOTING FORMULA:- 


Volume, 
V = (L x B x D) = H/3{A1 + A2 + sq.rt(A1+A2)}

Where A1 = L x B
A2 = l x b B
H = D-d (Overall depth of footing – depth of
 Rectangular footing.



CIVIL ENGNEERING STANDARD  DATAS | CIVIL ENGINEER BASIC KNOWLEDGE | CIVIL KNOWLEDGE | CIVIL ENGINEERING STANDARD INFORMATION |STANDARD MATERIALS AND STANDARD CALCULATION|PRODUCTIVITY OF WORK || BY UNIQ CIVIL ENGINEERING

          TRAPEZOIDAL FOOTING




*CMENT REQUIREMENTS:-

M10 : 210 Kg
M20 : 320 Kg
M25 : 340 Kg
M30 : 380 Kg
M35 : 410 Kg
M40 : 430 Kg
M45 : 450 Kg
M50 : 450 + M.S 7.5%

*Thumb rule requirement of standard materials and standard
calculation in high raised building:-


  1. Steel =3 to 5 kg / sft
  2. Cement =.5bags/ sft
  3. RMC =.05 m3/sft
  4. Block =12.5 nos /sqm
  5. Electrical cost = Rs 133/sft
  6. Plumbing cost = Rs 126/sft
  7. Fire fighting cost = Rs 40/sft
  8. External development = Rs 94.5/sft
  9. Civil works-Structure = RS 751.25/sft
  10. 200 mm in cm 1:6 =0.124Bags /sqm
  11. 200 mm in cm 1:4= 0.206 bags/sqm
  12. 150 mm in cm 1:6= 0.093 bags/sqm
  13. 150mm in cm 1:4= 0.144 bags/sqm
  14. 100 mm in cm 1:4= 0.103 bags/sqm
  15. Ceiling plastering= 0.11 bags/sqm
  16. Wall plastering =0.09 bags/sqm
  17. Rough plastering =0.09 bags/sqm
  18. Duct plastering= 0.09 bags/sqm
  19. External plastering= 0.175 bags/sqm
  20. lathen plastering =0.55 bags/sqm
  21. stucco plaster =0.175 bags/sqm
  22. 100 mm plaster band= 0.012 bags/rmt
  23. pcc 1: 4: 8= 3.4 bags/cum
  24. pcc 1:5:10= 2.52 bags/cum
  25. pcc 1:3:6= 4.2 bags/cum
  26. pcc 1:2:4 =6.02 bags/cum
  27. 230 mm brick =0.876 bags/cum
  28. 115 mm brick work= 0.218 bags/cum
  29. vdf 100 mm thick =0.82 bags/sqm
  30. granolithic flo oring 40 mm= 0.35 bags/sqm
  31. granolithic flooring 20 mm= 0.28 bags/sqm
  32. anti-skid= 0.28 bags/sqm.
  33. ceramic= 0.28 bags/sqm.
  34. vertified tile flooring =0.28 bags/sqm.
  35. vertified tile dado 0.27 bags/sqm.
  36. ceramic dado =0.27 bags/sqm.
  37. marble flooring =0.3 bags/sqm.
  38. 100 mm heigh marble skerting =0.027 bags/rmt.
  39. marble glading =0.27 bags/sqm.
  40. terracota tle flooring =0.3 bags/sqm.
  41. mangalore tile= 0.3 bags/sqm.
  42. Door frame fixing= 0.17 bags/sqm.
  43. water proofing for sunken slab= 0.23 bags/sqm.
  44. water proofing for walls= 0.23 bags/sqm
  45. water proofing for balcony/toilets =0.65 bags/sqm.


*Labour Productivity:-


Brick work :-
1 mason:-
1 Men mazdoor.                  1.25 cm
1 Women Mazdoor.

Wall Plastering :-
1 mason
1 Men mazdoor              10 sqm
1 Women Mazdoor

Ceiling Plastering :-
1 mason
 1 Men mazdoor              8 sqm
1 Women Mazdoor

External Plastering:-
 1 mason
 1 Men mazdoor.              8 sqm
 1 Women Mazdoor.

Blockk work 8”:-
 1 mason
 1 Men mazdoor              10 sqm
 1 Women Mazdoor.

Blockk work 6” :-
1 mason
1 Men mazdoor.                8 sqm
1 Women Mazdoor.

Blockk work 4” :-
1 mason
 1 Men mazdoor                8 sqm.
1 Women Mazdoor

Carpenter :-
1 Skilled
1 Un skilled:-                     4 Sqm

Bar bender :-
1 Skilled
 1 UN skilled                       200Kg

Tile work:-
 1 Mason
 1M Mazdoor.                   10 Sqm

Painter :-
skilled OBD     600 Sft
 Emulsion.       800 Sft.
Putty                600 Sft
 Primer.           800 Sft